I hope this does not duplicate this question. I tried to post it earlier and it looked like it froze up.
A PO was issued for an inventory item at an incorrect cost, then the item Shipment was received at the incorrect cost. Then the item was partially consumed in an assembly BOM. The finished good is then transferred to a different site.
Now the invoice comes in from the supplier at a lower cost. What is the best practice for getting the correct cost on the item?
Should I just do an enter match for the invoice with the correct cost, or do an Adjust Cost in the utilities?