I have problem with Pegged Supply orders not getting scheduled status.
The B#293 is the product which contain the pegged supply. By default is going to schedule status and then creating another production B#294 (pegged supply) but this order going to estimated status not scheduled.
Why? Is there any setup which I am missing?
Appreciate the help!
Hi,
If you firm an MRP generated planned production order then its directly derived planned production orders will be firmed as well provided that these pegged supply components have a coverage group different from Manual. The firmed pegged supply orders will then have status Scheduled.
But if you create a production order manually and then schedule that order, the scheduling engine will indeed generate the pegged supply production(s) with status Estimated. This is because the pegged supply order is generated during the estimation of the manually created production order. If you want the new pegged supply orders to be scheduled immediately when scheduling your new production order, you must enable the option "Schedule references" and optionally also "Synchronize references" in the Job scheduling dialog box.
Hope this helps.