RE: Pricing/Costing in Project operations non stocked implementation
Hi Mark,
Really appreciate you getting back to me so quickly.
When I check those particular transactions the cost transaction is linked to a price list but the unbilled sales have the price list blank as you said.
I have been through those steps and I am still struggling. I will explain findings in each step below:
1) I have multiple price lists of type (with context set to sales). I am just using the demo price lists at this stage.
2) The role prices have a price set against them. I am using the GBPM entity and the hour transactions are against the project manager role. I checked the categories tab and there wasnt an entry for "Time" category which I wasn't sure would make a difference or not as it should pick up from the role I assume? I added a Time category into the project price list with a price calculation to see if anything happened. No change with this either
3) This was the first promising sign of something that could be wrong. The price list for the roles in that entity were set to unit of "working day" where as the time entries were against "hour". So I changed one of the entries to have a unit of "hour". This actually made things worse. I was now not getting a value on the cost transaction which was really strange.
4) Wasn't quite sure what settings I should be looking for here. Certain place I should be looking? Checked the "organisational units" tab under settings but apart from adding a price list to the org unit, I couldnt see any other parameters that would effect the pricing.
5) Posted a journal with unbilled sales type as you suggested. When saving it wouldn't pick up a price list automatically. When I selected a price list manually and saved it then pulled through a price (although this price was different to what I had setup in the price list).
This is turning out to be longer than I thought haha.
Thanks
Amar