Calculate Item Cost funcionality

(0) ShareShare
ReportReport
Posted on by 15

Does anybody knows if is possible to Calculate Item Cost (standard cost) based on active trade agreements prices for a purchased item? Our customer´s request is to consider the trade agreements prices of an item instead of the last purchase price for the new standard cost. 

With this parameters we get a new pending standard cost based on the last purchase price but is not what we need: 

pastedimage1636046384617v1.png

Thank you 

I have the same question (0)
  • Ludwig Reinhard Profile Picture
    Microsoft Employee on at

    Hi,

    If I get you right then you want to have cost prices that consider the trade agreements that you have with your vendors. Is that right?

    Why would you need that?

    Wouldn't you get simply other trade agreement prices?

    I don't understand the reasoning behind.

    Would be great if you could elaborate.

    Many thanks,

    Ludwig

  • Sorana Profile Picture
    15 on at

    Hi Ludwig,

    Thank you for your answer.

    Our client needs to update the standard cost each semester and the request is: "it should consider the price that the next order would go through at".

    For example. From 01/07/2021 to 31/12/2021 the standard cost is 1 EUR. Last purchase price is 0.8 EUR and they renew the prices with one of the vendors to 1.1 EUR from 01.01.2022. They ask to calculate a new standard cost for the first semester of 2022 of 1.1 EUR.

    How do you think about this business process?

    Thank you in advance

  • Suggested answer
    Ludwig Reinhard Profile Picture
    Microsoft Employee on at

    Hi Sorana,

    The problem that I see from that is that you want to have a vendor specific 'standard cost price'.

    In my opinion that is not a standard cost price if you have a price of $1 for item X if it is purchased from vendor A and $1.5 for item X if it is purchased from vendor B.

    That is my understanding from what you mentioned.

    If my understanding is correct then I don't see the necessity of using standard costs.

    Best regards,

    Ludwig

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

#1
Martin Dráb Profile Picture

Martin Dráb 584 Most Valuable Professional

#2
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 499 Super User 2025 Season 2

#3
Sohaib Cheema Profile Picture

Sohaib Cheema 254 User Group Leader

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans