Hi,
I have now and then problems with crateing work for last pallet for an item.
Here Im ordering for transfer 6 PL of rawmaterial ( all I have on stock)
On-hand 6 PL
Now I release it to warehouse and I get this error message that not all pallets were fully allocated
When I look at works on load I see only 5 PL that are open work. It skips always last pallet.
I know that I will get it working if I change location but that is not a solution because we have same errors in our master warehouse on summit picking locations.
Do anybody have anykind of ideas how to get rid of this error/bug
Thanks,
sami
Hi, if your still having an issue, please create a support case and we troubleshoot the issue in more detail.
Hi,
I tested now second time to transfer 3 pallets of rawmaterial. I managed to allocated all 3 pallets but succeeded to create work for 2 pallets
Here is Wave history log.
Load error log
We don't use a load templete when transfering goods from rawmaterial warehouse to production.
Where can I verify location directives?
I don't use stocking limits for locations in rawmaterial warehouse so it's not an issue
Thanks,
sami
sami
Hi Sami,
Verify your Location Directives again and Unit of Measure Restrictions . What do you see in your work creation history?