Dear All My Client is a Rice Processing Company, what it does is purchase raw rice from market, process it and then export it. The Manufacturing process is as follow:
• Operation 1 Cleaning (Performed on cleaning section of Plant which has four machines all work together)
• Operation 2 Polishing (Performed on polishing section of Plant which has four machines, in some cases two machine1 and machine 2 is operated and in some cases machine 3 and machine 4 is operated whereas at times all four works together)
• Operation 3 Sorting (Performed on sorting section of Plant which has two machines, both works together)
• Operation 4 Grading 1 (Performed on 1st grading section of Plant which has four machines, all works together)
• Operation 5 Grading 2 (Performed on 2nd grading section of Plant which two four machines, both works together)
• Operation 6 Grading 3 (Performed on 3rd grading section of Plant which two three machines, all works together)
• Operation 7 Packing (Performed on packing section of Plant which one machine) The capacity of whole plant in which all the machines works together is 5 Ton per hour and all machines starts together, i.e. all the operations are simultaneous. In Microsoft Dynamics AX-2009 this can be achieved by defining secondary operations of one primary operation but it has a limitation that one operation can have only five secondary operations.
What should be done in this case? Please help!!
Thanks in advance
Regards
Muhammad Saad