I have one scenario:
1. I have added a task by name Task1 under schedule tab of 8 hours.
2. I have assigned a resource for this Task1 for 8 hours.
3. In resource assignment tab i can see 8 hour allocated.
4. Now resource has worked for 4 hours and has got approval for 4 hours.
5. Now tracking tab shows correctly where Effort hours = 8 , Remaining hours = 4 , Progress = 50% , Actual hours = 4 , Efforts estimate at complete (EAC) = 8 , schedule variance = 0.
6. Now i am going in Resource Assignment tab and i update 2 hours for same Task = Task1
7. Now when i do refresh in schedule tab , i updates it to 2 hours for Task1.
But i am facing issues for Tracking Tab , it is updating remaining hours wrongly as given below
Tracking tab : Efforts = 2 , Remaining hours = 4 , Progress = 50%, Actual hours = 4 , Efforts estimate at complete (EAC) = 8 , schedule variance = -6
Can anyone suggest why remaining hours is not updating to 0 as i have already approved time entry for 4 hours?
I have already done refreshing so many times