As i have activated the budget control for projects, the item is already under budget, but all the purchase orders gives error related to the budget as below:
The entry for category 'PS-Item', activity '005377' on project 'PRJ-000031' cannot be posted/approved because it would cause the cost budget to be exceeded by 4,000.00.
any recommendations in the budget control configuration or projects setup ?