I have a very strange situation with the net requirements of a product (attached the screenshot) that has some on-hand, only one sales order and only one production order to fully satisfy the demand.
The production order is not pegged against the demand and instead AX is proposing a planned production order.
I digged into coverage group (that is used by hundreds of other products), and all the possible parameters I'm aware of , rerun multiple times the MRP though not able to make AX peg the demand against the production order.
What it could be?
Hi Sjoe,
I replicated the same scenario on a latest version D365, with the same results.
Between the Production order and the Sales order there are 66 days and the Negative days are set to only 30.
Then I changed the negative days to 70 and the Production order was pegged to the demand.
Hope this helps.