Hello Dynamics Community,
Production orders generate "Planned production orders" for lower level BOM requirements automatically - and this is fine.
However, we are spending great amounts of resources for "Firming" or "Approving" those "Planned production orders" that have sufficient inventory.
Can we automate this process? such that production order requirements for level BOM requirements automatically start the production of those relevant production orders to feed the higher level BOM items.
Alternatively we are interested in finding out how to quickly view, which "Planned production orders" we can start, that will not run into the problem of empty inventory to feed those planned production orders.
Thanks in advance!
Best regards Peter Vesterager