Query regarding Accrued Revenue settlement in FP Project

(0) ShareShare
ReportReport
Posted on by

Hi All,

I have one doubt regarding Accrued Revenue account in FP Project, On posting the estimates for FP Project system Debit the WIP-Invoices on account A/C and Credit - Accrued Revenue - Sales Values A/C, but the accrued revenue account doesn't get settled on closing the project.

Can someone help me with the process to settle the accrued revenue account ?

*This post is locked for comments

I have the same question (0)
  • Suggested answer
    Ludwig Reinhard Profile Picture
    Microsoft Employee on at

    Hi Nakul Waghe,

    Have you eliminated your estimates before closing the project?

    Best regards,

    Ludwig

  • Community Member Profile Picture
    on at

    Yes, I did. It just posted Dr. and Cr. entry in WIP accounts but no effect on Accrued Revenue.

  • Suggested answer
    Ludwig Reinhard Profile Picture
    Microsoft Employee on at

    Hi

    Have you checked LCS for an available hotfix? If you run an older system the behavior you experience might be causes by a bug.

    If you are operating the latest version then please share some additional details of your project group setup and the transactions that have been recorded.

    Many thanks

    Ludwig

  • Community Member Profile Picture
    on at

    Hi Ludwig,

    Thanks for the reply, I am using latest version of D365, I have done the following configuration at Project group level:

    Post Cost Hours, Post Cost Items and Post cost Expense to - P&L.

    Post On-Account invoicing to - Balance.

    Revenue Recognition Method - Completed Percentage.

    Accrue Revenue as - No (By Default)

    Transaction entries:

    Cost posting entry:  - Cost of Project - Expense Dr. 

                                                                                          Offset Account A/C Cr.

    Milestone Posting: - AR Dr. to

                                                   WIP-Invoiced on-account A/C Cr.

    Estimation Posting: - WIP - Invoiced on-account Dr. 

                                                                                        Accrued Revenue A/C Cr.

    Elimination:  Project - WIP Invoiced on-account Dr.

                                                                                     Project - WIP - sales value 

    So the finally I end up with - AR Dr. to 

                                                                 Accrued Revenue A/C Cr.

  • Suggested answer
    Ludwig Reinhard Profile Picture
    Microsoft Employee on at

    Hi,

    WIP - Invoiced on-account

    is this your ledger account or the posting type?

    Did you use the same WIP account multiple times?

    Best regards,

    Ludwig

  • Community Member Profile Picture
    on at

    This is my Ledger account. The posting type is - Project-WIP Invoiced on account Dr. to Project-WIP-Sales values Cr.

  • Ludwig Reinhard Profile Picture
    Microsoft Employee on at

    So, you have separate WiP accounts, right?

    Can you share the vouchers that have been posted incl. the posting types used?

    Best regards,

    Ludwig

  • Community Member Profile Picture
    on at

    Hi Ludwig,

    Sharing the screenshots:

    Cost Posting

    Elimination-posting.PNG

    On-Account Posting

    On_2D00_Account-milestone-posting.PNG

    Estimation Posting

    Estimation-posting.PNG

    Elimination Posting

    Elimination-posting.PNG

  • Suggested answer
    Ludwig Reinhard Profile Picture
    Microsoft Employee on at

    Hi,

    From my perspective I cannot see that something is wrong here

    8156.pro.png

    The first posting records the costs on your project (highlighted in red)

    The second posting records the receivable against the customer

    The third posting records the Revenue throught the estimate posting

    The last posting clears the WIP accounts.

    What remains are the costs (red) and the revenue (green)

    Note: The only thing that looks a bit strange is the first posting that uses the travel expense account as the offset account. In my opinion this should be an Accounts Payable summary account, i.e. a vendor account.

    Everything else look ok to me.

    What is it that bothers you exactly here?

    Best regards,

    Ludwig

  • Community Member Profile Picture
    on at

    Hi Ludwig,

    My query is regarding the Project accrued revenue account which is getting hit on posting estimate. How that accrued revenue account will be nullified because even after closing the project, Project statement report shows this amount as accrued revenue. 

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > 🔒一 Microsoft Dynamics AX (Archived)

#1
Martin Dráb Profile Picture

Martin Dráb 4 Most Valuable Professional

#1
Priya_K Profile Picture

Priya_K 4

#3
MyDynamicsNAV Profile Picture

MyDynamicsNAV 2

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans