Hi,
I am seeking help with an issue. I have an investment project where I have enabled budgeting for control. When I am running estimates, my cost to amount is getting 2 times if I run estimation 2 times, 3 times if I run it 3 times and 4 times and so on so forth. This is beyond my understanding.
Please see the details below for project approved budget:
I have posted transactions like the following: Hour total = $900 and Item for $5000. So % completion = 98.33%
I have no forecast setup and my budget is tied to original forecast which I would like to copy for the forecast
It says 8% completed which is not correct
Why, because it is changing this amount every time I run and has reached to 11100 and 55000
I am not sure why this cost to complete is getting increased, any help?
Cost template setup is like this