When I create a new project I cannot find the section to open the work breakdown structure but instead there is a tab called schedule (s. screenshot). Is schedule supposed to be the same as wbs?
I am also trying to figure out how to enable changing tasks (e.g. task name), because once a task is created changes are not applied. Is there a way to enable changing tasks?
My last question: Am I able to define tasks as milestones within the wbs/schedule?
Thanks for your support.
Jasmin
As far as I know, there currently is no milestone support inside PSA. You can set Milestones using MS Project. Or is there any other way to do it atm?
Hi Jasmin. You're correct that Schedule is now what WBS used to be in V1 and V2 of PSA. You should be able to edit a task's name by clicking on it and renaming it. Or by changing it from the project task entity.
Tasks can't be defined as a milestone but you can relate a milestone to a task when you're creating new milestones on a Project Contract. Let me know if you want a screen capture.