We experience issue with operation scheduling with finite capacity where the secondary resource gets overbooked.
Our set ups are as follows.
Any idea of what could cause this unexpected result?
Thanks in advance
1.Master planning parameters
With /Accurate finite capacity for Operation Scheduling/ turned on to solve /Master planning doesn't seem to respect capacity limitations and is scheduling more than the available capacity/ as per MS documentation : <https://learn.microsoft.com/en-us/troubleshoot/dynamics-365/supply-chain/planning/master-planning-not-respect-capacity-limitations>
2.Master plan set up as follows :
3.The route is set up as follows with 2 operations, 1 primary and a secondary :
Set up of the primary operation :
Set up of the secondary operation :
4.Resource group set up
Primary resource group set up
Secondary resource group set up
5.Result of master planning run with or without planning optimisation:
Our primary resource doesn't get overbooked on 24th of june 2024 :
On 24th of June 2024 our secondary resource gets overbooked :