Hi everybody
I would like to ask about how AX system can calculate work-in-process cost and ending work-in-process cost in single production order
With my knowledge, we need to end production order to record financial amount of picking list journal, route card...=> accumulate to Work-in-process cost ( or Manufacturing cost) . However, if we end production order, system also allocate all value to Cost of goods manufactured at the same time. => In the system, there are no middle step to calculate ending work-in-process
In other hand, if we just only report as finish the production order. The manufacturing cost will be accumulated from physical amount. And I think it is not correct.
Have you ever faced with this situation? Please help me explain
Thanks you guys very much