Dear All.
Please help.
I have production order, delivery date is at 21th May 2019,
when I scheduling this production order using backward from delivery date, then result is => start date setted to 7th May 2019 and End date at 6th Jan 2020.
how I can check why the end date finish in the next 7 months later, our leadtime is 1 week.
how I check the other production order to make sure if other production order already occupied july until December 2019.
please help, thank you

*This post is locked for comments
I have the same question (0)