Dear All.
Please help.
I have production order, delivery date is at 21th May 2019,
when I scheduling this production order using backward from delivery date, then result is => start date setted to 7th May 2019 and End date at 6th Jan 2020.
how I can check why the end date finish in the next 7 months later, our leadtime is 1 week.
how I check the other production order to make sure if other production order already occupied july until December 2019.
please help, thank you
*This post is locked for comments
Hi Andre,
thank you for your help,
yes, just found out, calender not setted correctly, the efficiency percentage not set correctly.
appreaciate your help.
Hi Benjamin,
Can you check if the calendars are setup correctly? Do you have limited capacity enabled and is there any bottleneck?
Stay up to date on forum activity by subscribing. You can also customize your in-app and email Notification settings across all subscriptions.
André Arnaud de Cal... 291,240 Super User 2024 Season 2
Martin Dráb 230,149 Most Valuable Professional
nmaenpaa 101,156