Hello Dears,
I've few questions about Project and Accounting Module.
we have few projects internally and we need only to use and apply the WBS to manage and track the projects and tasks, do we need to create project contract and project quotation?
also, I've created a test project and I want to create for it WBS but I receive this issues 'Activities cannot be created when the number sequence for the hierarchy ID is set to Manual. Change the number sequence value on the Number sequence references form.' do you know why?
Lastly, do you know any good examples that i can follow? i found on YouTube but perhaps you guys know something special.
Thanks all!