AX2012R2 - Creating new fixed price Project --- where do we enter contract value

(0) ShareShare
ReportReport
Posted on by

We are new to AX and running 2012 R2. We thought something worked one way, but something else seems to be happening. We're hoping someone can assist.

We used the wizard to create a Project Contract.

We created a new Fixed Price Project.

Where do we put in Contract Value? We tried to enter it as an On account transaction. Then we created an invoice. The Estimates do not show it correctly because the add the 2 values together for Accrued revenue sales value.

thanks

*This post is locked for comments

I have the same question (0)
  • David Massey Profile Picture
    on at

    The contract value is the sum of the On-account transactions.  Please explain further what you mean by "estimates" do you show correctly.  Are you using billing rules on the contract?

  • Community Member Profile Picture
    on at

    Do we need to enter ALL milestone billings upfront and then invoice them as they come due?

  • Community Member Profile Picture
    on at

    Estimates:

    Project management and accounting

    Common

    Projects

    All Projects

    - select one

    Manage tab

    Estimates

  • Verified answer
    David Massey Profile Picture
    on at

    In a Fixed Price project, amounts invoiced and the amount recognized as revenue are not the same thing.  The On-Account transactions represent the amount of the contract whether or not they have been invoiced.  These transactions can be invoiced at any point during the management of the project.

    The amount of revenue recognized is based on the Fixed price revenue model. (Completed Contract or Percent complete).

    There are a number of parameters in the Create Estimate form (Revenue Recognition) that control the values displayed in the various grids as they give information about accepting the amount(s) to be recognized as calculated by the system or overridden to use an "observed calculation" of revenue to be recognized.

    One other thing to consider is whether you need to account for your costs and revenue using a Fixed Price model or is this the project in the form of Time and Material using progress billing, milestones, Not-to-Exceed for your accounting requirements.

  • Community Member Profile Picture
    on at

    Thanks David!

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > 🔒一 Microsoft Dynamics AX (Archived)

#1
Martin Dráb Profile Picture

Martin Dráb 4 Most Valuable Professional

#1
Priya_K Profile Picture

Priya_K 4

#3
MyDynamicsNAV Profile Picture

MyDynamicsNAV 2

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans