Dears 

good day , Hope you are well 

I have an issue , & Hope you will help me 

when I Record Sales Forecast to an item with BOM & Distribute its plan on several Months by using Method 'Period or Key'

then i go to run  ''forecast Scheduling'' for this plan & the result generated perfectly - needed items distrusted on moths according to required plan- ( Gross requirements)

the Problem appears in running of ''Master Scheduling '' the Net Requirements are not shown all they show only 2 months 

notable that the setup of coverage group is Period 

Categories:
  • RE: Master Scheduling Results

    Dear Christoph

    Many thanks for your response

    it's working now

  • Verified answer
    Christoph Thaler Profile Picture
    Christoph Thaler 5,442 on at
    RE: Master Scheduling Results

    Hi Mohamed.Godah,

    Please check the setup of your coverage group „Period“. There should be some fields to define the period. With this parameter you tell the system the time fence into the future to be calculated in MRP. If requirements are outside the time fence they are not calculated.

Helpful resources

Quick Links

Replay now available! Dynamics 365 Community Call (CRM Edition)

Catch up on the first D365 Community Call held on 7/10

Community Spotlight of the Month

Kudos to Saurav Dhyani!

Congratulations to the June Top 10 community leaders!

These stars go above and beyond . . .

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 287,696 Super User

#2
Martin Dráb Profile Picture

Martin Dráb 225,490 Super User

#3
nmaenpaa Profile Picture

nmaenpaa 101,148

Leaderboard

Featured topics

Product updates

Dynamics 365 release plans