Dears
good day , Hope you are well
I have an issue , & Hope you will help me
when I Record Sales Forecast to an item with BOM & Distribute its plan on several Months by using Method 'Period or Key'
then i go to run ''forecast Scheduling'' for this plan & the result generated perfectly - needed items distrusted on moths according to required plan- ( Gross requirements)
the Problem appears in running of ''Master Scheduling '' the Net Requirements are not shown all they show only 2 months
notable that the setup of coverage group is Period
Dear Christoph
Many thanks for your response
it's working now
Hi Mohamed.Godah,
Please check the setup of your coverage group „Period“. There should be some fields to define the period. With this parameter you tell the system the time fence into the future to be calculated in MRP. If requirements are outside the time fence they are not calculated.
Stay up to date on forum activity by subscribing. You can also customize your in-app and email Notification settings across all subscriptions.
André Arnaud de Cal... 291,253 Super User 2024 Season 2
Martin Dráb 230,188 Most Valuable Professional
nmaenpaa 101,156