Multiple resources with different working hours on one operation

(0) ShareShare
ReportReport
Posted on by 45

Hi.

I'm trying to get AX help tell my workers what operations / productions they are expected to work on according to the scheduling in AX.

My issue at the moment is that I have a machine (primary operation) and several operators (secondary operation). The 2 operators (Human resources) I have available have different working hours, one is from 7.00 - 14.30, the other has from 15.00 - 23.00.
The machine has working hours from 00.01 to 23.59.

When scheduling the production AX will only schedule one resource for the secondary operation typical the resource with hours from 7.00 to 14.30.
I cant seam to get AX to use the second resource also, so that capacity reservations for the machine would be both 7.00 - 14.30 and 15.00 - 23.00, so a production that takes 12 hours to complete can be done in one day.

I have tried to set the secondary operation to allow the use of 2 resources, but this does not work either
the 2 resources are in the same group, but as mentioned with different working hours. 

Any thoughts or ideas as how to solve this ?

I have the same question (0)
  • Austin Shen Profile Picture
    on at
    RE: Multiple resources with different working hours on one operation

    Hi Brian.s,

    Would you mind sharing how your resources and route are set? Thank you.

    Best Regards,

    Austin Shen

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Mansi Soni – Community Spotlight

We are honored to recognize Mansi Soni as our August 2025 Community…

Congratulations to the July Top 10 Community Leaders!

These are the community rock stars!

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

#1
Sohaib Cheema Profile Picture

Sohaib Cheema 665 User Group Leader

#2
Martin Dráb Profile Picture

Martin Dráb 595 Most Valuable Professional

#3
Yng Lih Profile Picture

Yng Lih 558

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans