BOM costing version in AX 2012 R3

(0) ShareShare
ReportReport
Posted on by 1,260

Hi,

I am wondering if it is possible to do multiple item calculation for BOM in ax 2012 r3 in a similar way we do for single item calculation.

As in right now the out of box functionality, allows us to add a quantity for one item at a time, is there a way or how can I modify or change this functionality and allow the quantity field to get display when multiple item is created - such that we can add quantity value for multiple items at a time.

*This post is locked for comments

I have the same question (0)
  • Nancy_Nancy Profile Picture
    85 on at
    RE: BOM costing version in AX 2012 R3

    any update? i have the same issue

  • Daljit Kaur Rahsi Profile Picture
    1,260 on at
    RE: BOM costing version in AX 2012 R3

    Okarnaukhov,

    This will add the quantity only for one item. Whereas I want to change the quantity value for multiple items at one.

    Assume the quantity for items 111, 123, 1234, 12345, ..... 100090, 100091, 100092 is 50.00. So for all this items I want the 50.00 value to be changed to 20,000.00 at once. Instead of opening and calculating one by one for all this items.

    How can I do that?

  • okarnaukhov Profile Picture
    118 on at
    RE: BOM costing version in AX 2012 R3

    Go to Released products/Action pane/Manage costs>Item price

    In this form, you can calculate your price per multiple quantities

    1185.c1.PNG

  • Daljit Kaur Rahsi Profile Picture
    1,260 on at
    RE: BOM costing version in AX 2012 R3

    Fredrick,

    I want to input the quantity when I am selecting multiple items from the below form:

    1832.BOM-4.PNG

    Such that when the item ID is created under the item price the user added quantity should also show up instead of the default values in the following two form:

    1832.BOM-4.PNG

    Last.PNG

    Right now the quantity from the two forms are using the default value on creation and so we have to manually go one by one and perform single item calculation.

    Whereas, we have a bunch of item where the demand for quantity is 100000 or so, whereas the default is 50. So 2000 or 2500 items need to be manually done and change the quantity, any way to update the quantity all at once from both the form.

    I cannot change the default quantity as on the production or manufacturing 50 value works proper for them.

  • Fredrik Sætre Profile Picture
    12,644 on at
    RE: BOM costing version in AX 2012 R3

    You should be able to do the exact same procedure for a BOM item... At what time do you want to do the calculation? If it is price versions you want, you can input quantity for the calculation.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Mansi Soni – Community Spotlight

We are honored to recognize Mansi Soni as our August 2025 Community…

Congratulations to the July Top 10 Community Leaders!

These are the community rock stars!

Leaderboard > 🔒一 Microsoft Dynamics AX (Archived)

#1
Syed Haris Shah Profile Picture

Syed Haris Shah 9

#2
Mea_ Profile Picture

Mea_ 4

#3
KP-31070522-0 Profile Picture

KP-31070522-0 3

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans