Hi,
Can you tell us what exactly you want to adjust? You can adjust project transactions itself, or only project transactions on ledger levels.
Here is a quick guide how to adjust project transactions:
1: with Adjust transactions you can pull some lines by parameters (see below) for a given project
2: Under posted transactions you can select the exact line you want to adjust under Process\Adjust transactions
1.: Click select
2.: select by parameters which project transactions you would like to see. You can select the appropriate line(s) to adjust them. Once done, all lines will appear in (4). You can select all of the lines or just one or multiple, depending which lines you would like to adjust.
3.: Click adjust. A form will open, where you can choose if you would like to change all lines with given parameters. F.e. you can tell the system to pull the sales prices, financial dimensions, line property etc. automatically. You can also leave everything to "No" and adjust the line(s) manually.
4.: As stated before, you will see here the originally transactions. You can select one, multiple or all lines here to adjust them.
5.: Here you will see a list of transactions from (4) which you can adjust manually, or they might be already changed, depending if you selected something under adjust (3).
6.: Once you are done comparing the original transactions from (4) and the new transactions from (5), you can post it.
Kind regards, Adis