Creating a PO from a project SO records double billable transactions

(0) ShareShare
ReportReport
Posted on by 10

When we create a PO from a Project SO, once the PO is invoiced it records a billable transaction. As soon we invoice the SO the revenue is recorded twice. Does anyone know what causes this?

I have the same question (0)
  • André Arnaud de Calavon Profile Picture
    306,446 Super User 2026 Season 1 on at

    Hi 365Consultancy,

    Can you tell the steps you have performed to create the PO? What project line property is set on the PO lines and did you specify a project sales amount? If the PO has a reference to the project and the line property is having a chargeable line property, then both the sales order and the PO will indeed create billable transactions.

  • 365Consultancy Profile Picture
    10 on at

    Hi André,

    Thanks for your reply. Steps are:

    1. Create a SO from the project

    2. From the SO under tab sales order create a PO (not direct delivery)

    Line property on SO is billable with a reference to a project and these are defaulted to the PO from SO which is also billable. Item has fixed sales and purchase set on the item form or coming from trade agreements.

    Isn't this a bug? Because the revenue should be taken from SO and costs from the PO.

  • Suggested answer
    MauricioSaldana Profile Picture
    Microsoft Employee on at

    Hi 365Consultancy,

    This is a known issue and we are having an internal ticket to resolve it, I would suggest you to open a support case so we can add your case into the internal ticket this will help us prioritize a solution.

    This error occurs when using service items on a PO so there is a workaround where service items can be configured as stocked items on the item model group. In this case service items can work as stocked items from cost perspective. In case if there are fewer service items used in the projects new service items can be created and old one can be blocked using default order settings.

    BR

    Mauricio

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Season of Sharing Community Challenge Winners!

Congratulations to our community stars!

Women in Power Builds Momentum

Expanding mentorship, skilling, and AI innovation

Congratulations to the June Top 10 Community Leaders

These are the community rock stars!

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 385 Super User 2026 Season 1

#2
Subra Profile Picture

Subra 270

#3
Martin Dráb Profile Picture

Martin Dráb 243 Most Valuable Professional

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans