Actual Labor Cost Not Calculating

(0) ShareShare
ReportReport
Posted on by 195

Hi,

We are testing PSA and have set up an internal project.

We have submitted 2 time sheets totaling 80 hours over 2 tasks.

The price list is set up and in the Actuals view you can see all of the time submitted to the project. 

In addition, you can see that the price list has been applied in the Amounts column.

However, the total Actual Labor cost is not adding up to the individual task totals.

PSA_5F00_Cost.JPG

We have tried it if different browsers too just in case it was a browser issue.

Are we missing a checkbox or field somewhere?

Any suggestions appreciated.

Jason

I have the same question (0)
  • Suggested answer
    Matthew Lazowski Profile Picture
    3,163 on at

    Hi Jason,

    This should work.

    Check if OOTB workflows and plugins are enabled.

    You can log a support request if it still doesn't work.

    Kind regards,

    Matthew

  • Suggested answer
    JasonTwi Profile Picture
    195 on at

    This turned out to be a software bug!

    MS have said it will be addressed in future updates.

    The workaround is to create WBS structures with at least 3 levels, which for us was fine but may not be for everyone.

  • Ann_BE Profile Picture
    10 on at

    Hi,

    Is there any update on this issue? Or someone found another workaround somehow?

  • JasonTwi Profile Picture
    195 on at

    Hi,

    I’m not aware of an update. 
    we are running with the three level WBS and it’s fine. 

    jason

  • Ann_BE Profile Picture
    10 on at

    Hi Jason, Thank you for your answer. I've tried the 'three level WBS' but still no cost and billing estimates of the resources. Except when working with generic resources... See the screenshots below... Any idea?

    pastedimage1620841688395v1.png

    pastedimage1620841855633v2.png

  • JasonTwi Profile Picture
    195 on at

    Hi,

    Are the costs set up for the roles you have assigned each person?

    As you probably know each user has to have a role assigned in the project

    with an associated cost.

    You could also make sure that time entries are approved, which I guess they are.

    Do you have a sandbox instance to test out other ideas or options?

    This can help a lot as we used two test accounts to run tests,

    A standard time entry user logged in via an incognito session in Chrome and then the supervisor

    logged in a standard Chrome session. This allowed us to enter time and approve and see results directly and quickly. Just try a very basic project and see if the costs work, if so then move onto the next step until the issue appears.

    Have you raised it with Microsoft? You can mention that I raised a similar issue last year.

    Sorry I can't be more help.

    Regards,

    Jason

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

#1
Martin Dráb Profile Picture

Martin Dráb 544 Most Valuable Professional

#2
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 450 Super User 2025 Season 2

#3
Sohaib Cheema Profile Picture

Sohaib Cheema 250 User Group Leader

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans