Hello experts, 

I am currently setting up a freight surcharge on all purchase orders, with the functionality that is available in the costing sheet (type: cost of purchase). However, I have encountered an issue. AX seems to be calculating the surcharge two times. Let me explain the scenario.

The calculation basis for the surcharge is the cost groups for the purchased items with a percentage of 2,5%.


Lets say i purchase an item, call it  item "100", with the following details:

  • STD-cost
  • Price in the purchase tab in item details: 8,00
  • Price in the manage costs tab in item details: 8,20 (this is the calculated STD-cost price, 8,00*1,025=8,20). This is the active cost in the costing version. If i click calculation details for this price, i see a base price of 8,00 and a surcharge of 0,2

When i do a product receipt on an order with 10 qty of item 100, I should get the following postings:

  • Credit 82,00 on my inventory account
  • Debit 2,00 on my indirect cost account (from the freight surcharge)
  • Debit 80 on the purchase accrual account

However, i get the following postings:

  • Credit 82,00 on my inventory account
  • Debit 2,05 on my indirect cost account
  • Credit 0,05 on my purchase price variance account
  • Debit 80,00 on my purchase accrual account

So the issue is that AX seems to be calculating the surcharge twice, resulting in a "surcharge on the surcharge". Any ideas of what might be causing this issue?

I know there are alot of parameters that can affect the result, if you need any more details than the ones speciefied above just tell me and i will post them here.


I am running AX 2012 R3 CU11

*This post is locked for comments

I have the same question (0)
  • Verified answer
    Community Member Profile Picture
    on at

    I solved the issue by going into inventory and warehouse management parameters -> bills of materials

    Under cost control i set Cost breakdown: sub ledger, variances to standard: per cost group

    After that i did a new calculation of my standard cost prices

    Im not sure why these changes made it work properly for me, can anyone explain?

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > 🔒一 Microsoft Dynamics AX (Archived)

#1
Martin Dráb Profile Picture

Martin Dráb 4 Most Valuable Professional

#1
Priya_K Profile Picture

Priya_K 4

#3
MyDynamicsNAV Profile Picture

MyDynamicsNAV 2

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans