Microsoft Dynamics AX (Archived)

Purchase order not appearing in Net Requirement of an item

Posted on by 681

Hi,

I am encountering an issue with net requirement of an item where the manually created purchase order is not appearing in Net requirements of an item. Even we have created purchase order, system is generating planned purchase order on master planning. Below are the on-hand details of an item and setup for Master planing.

4075.On_2D00_hand.PNG

7608.Net-requirement.PNG

Master plan settings:

plan-1.PNG

plan-2.PNG

plan-3.PNG

If anyone can help me on this.

Regards,

Ali 

*This post is locked for comments

  • guk1964 Profile Picture
    guk1964 10,877 on at
    RE: Purchase order not appearing in Net Requirement of an item

    There seems to be some inconsistency of settings e.g. your Max is 12 but you have ordered 24

    You have set a Min of 10 but you have set a policy not to reorder till stock runs out (ie.zero)

  • zeeshan.shaikh Profile Picture
    zeeshan.shaikh 681 on at
    RE: Purchase order not appearing in Net Requirement of an item

    Hi,

    Please see answers to your questions:

    1. Did you run a full regen mrp or a dynamic net change plan? I have run regen mrp for only this item

    2. Is the planned requirement for a different quantity or for an earlier requirement date? The requirement was for min max of the item coverage

    3. Do you have any action messages - e.g to cancel an order? No

    4. Did the manual PO go through an approval process if so, then what is the approval status? It is a confirmed PO

    5. Did the planned requirement exist before the manual order was created, if so then was that inside the freeze time fence? No manual order was created before running the MRP.

    6. is this Po for a BOM line type of vendor? Can you explain this more, the production type of item in PO is not BOM.

    In addition, i have already deleted all planned orders still the PO is not appearing in net requirements.

    Regards,

    Ali Zeeshan

  • Suggested answer
    guk1964 Profile Picture
    guk1964 10,877 on at
    RE: Purchase order not appearing in Net Requirement of an item

    Some things to consider:

    Did you run a full regen mrp or a dynamic net change plan?

    Is the planned requirement for a different quantity or for an earlier requirement date?

    Do you have any action messages - e.g to cancel an order?

    Did the manual PO go through an approval process if so, then what is the approval status?

    Did the planned requirement exist before the manual order was created, if so then was that inside the freeze time fence?

    is this Po for a BOM line type of vendor?

    Approved planned orders are treated as if they have been scheduled for the specified quantity and due date, and they will not be automatically deleted by master scheduling logic or the Delete Plan task.  A planned order is initially assigned a status of "Unprocessed" whether it is manually created or generated by master scheduling logic, and approving a planned order updates the status to "Approved".  An approved planned order must still be firmed to create an actual supply order. So maybe your planned order is in an approved status but not yet firmed/released?

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

December Spotlight Star - Muhammad Affan

Congratulations to a top community star!

Top 10 leaders for November!

Congratulations to our November super stars!

Tips for Writing Effective Suggested Answers

Best practices for providing successful forum answers ✍️

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 291,280 Super User 2024 Season 2

#2
Martin Dráb Profile Picture

Martin Dráb 230,214 Most Valuable Professional

#3
nmaenpaa Profile Picture

nmaenpaa 101,156

Leaderboard

Featured topics

Product updates

Dynamics 365 release plans