Project Budget commitment release on cancellation of PO

(0) ShareShare
ReportReport
Posted on by 147

Hello Champs !

 Need your help regarding project budgeting.

Background: When we make a purchase requisition from the project, the project budget gets committed. Subsequently, when we make a PO from that requisition and confirm it, the commitment is released. 

Question : How can we remove the commitment when instead of confirming the PO, we have to CANCEL it?
The PO has been cancelled, but the commitment has not been released. I don't seem to find any option.

Please suggest.

Thanks and regards,

Ahmed Nurullah.

*This post is locked for comments

  • G-Squared Profile Picture
    244 on at

    Good question.  I'm also looking for this answer.

  • Suggested answer
    G-Squared Profile Picture
    244 on at

    Update: I cancelled one of the PO Lines and it re-opened one of the Purchase Requisition lines.  I cancelled the Purchase Requisition Line and it un-committed the Project Budget funds and they became available again in Remaining Funds.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Season of Sharing Community Challenge Winners!

Congratulations to our community stars!

Women in Power Builds Momentum

Expanding mentorship, skilling, and AI innovation

Leaderboard > 🔒一 Microsoft Dynamics AX (Archived)

#1
Prashant Singh Profile Picture

Prashant Singh 2

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans