Hello everyone
I'd like to know if there is any impact of the Reorder Cycle when we run the planning worksheet.
For one item, I have the following setup in the FastTab Planning of the stockkeeping unit card :
Reordering Policy : Lot-for-Lot
Include inventory : yes
Reorder cycle : 6D
Safety Stock: 96
Minimum Order Quantity : 48
Order Multiple : 48
For the stock balance we have 99 units. There is a weekly forecast of 35 pcs.
When I run the Planning Worksheet, some results do not make sense. I have a suggestion of 192 units to order and sometimes the system suggests 2 purchase orders of 48 pcs each in the same week which is too much.
If i keep the reorder cycle empty, i have a suggestion of 48 units each week.
Is there any issue when a reorder cycle is combined with a safety stock? or any other issues related to the reorder cycle?
Thanks