Hi everyone,
I've been struggling to work with resource groups and work orders that take the whole day.
I've set the working hours for every resource as 9 to 5 to accommodate a 'normal' working day.
When I add a requirement group to the work order, which takes 8 hours, so the whole day, I am not able to find any resources on the schedule board.
I found out that the schedule board is taking into account the travel time.
When I set the advanced filter to 'Ignore Travel Time', nothing happens.
When I change the 'Available Duration' to 6 hours, all of a sudden there are resources available.
With that, I see that the schedule board is still taking the travel time into account, even though I specifically told them not to.
Am I doing something wrong?
Would love to get some help with this issue.
Thanks in advance!