Production protocol -BOM within a BOM-

(0) ShareShare
ReportReport
Posted on by

Hallo guys!

I have a question regarding production protocols. We tell the program to produce lets say a bottle a of wine. This bottle of wine is a bom within a bom, so lit , bottle, label and then the wine( which it has its own bom). Now well, is the system capable , when we ask it to produce 10 bottles to look at the lager, and say ok, in this bin there are enough lits in this other enough bottles etc.. but in this one there is not enough wine, I need actually 5 more liters of wine, but instead of triggering an extra production order for this 5 liters of wine, to triggers a production order for 5000L as I want to have the bin (tank) where i have the wine at at least 4500 L of capacity? and obviously at the same time, yielding purchasing orders lets say for grapes, water and whatever else the wine is made of , so the production order from the beginning can be fullfilled on time?

Thanks again!

*This post is locked for comments

I have the same question (0)
  • Suggested answer
    Community Member Profile Picture
    on at

    I believe, you can achiev this in NAV. It is designed to meet such requirements.

    You need to understand the various planning parameters and setup correctly to get the desired results.

    Using Order Multiple, you can achieve this.

    Refer following link for better understanding.

    msdn.microsoft.com/.../hh997398(v=nav.90).aspx

  • Community Member Profile Picture
    on at

    Thnaks, I was playing with that but i started getting errors, couldnt planned because a location was deleted, and although I made sure that no links existed for that location , it kept coming up..Ill forward this problem to some company, then I get now this other problem when I try to run the plan worksheet..really getting sick of it  .. :

    NO PRODUCTION PROTOCOL VERSION FOUND FOR VERSION iTEM NO. 01A0006.VARIANT CODE. QUANTITY 20002.DATE 21.02.16 (PROD.PROT.NO.H10011).

    How can poissibly one can make sense out of that...no production version found but then it gives me the prod.protocol from that item? it is this prod.protocol. obviously certified and ready to go..

    I just dont get it..

  • Suggested answer
    Community Member Profile Picture
    on at

    You need to make sure that all the BOM versions are certified (MANUALLY).

    Can you recheck and attach the exact error screen shot here?

  • Community Member Profile Picture
    on at

    Yes , I did that, all were already certified. the problem , after a few hours, was that I was the date, the prod.protocol. "creation" date was after the date that the whole planning was supposed to start. That gave me the error.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > 🔒一 Microsoft Dynamics NAV (Archived)

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans