Hello everyone,
I have a quick question regarding routings, run times, etc.
Here are details below regarding my capacity.
- I have one Machine "Big Mill" that can produce the following: 4600lbs/hour, 76.67lbs/Min, 1.278lbs/Second, 0.01304min/1lbs
I have my routing, machines, work centers, production bom, etc all set up in LBS.
Production BOM is set up in lbs. I have two items that go into the BOM. Item 1 = .60, Item 2 = .40........ total = 1.
For Routings I entered 0.01304min in the run time because thats what it takes me to produce 1lb.
However when I use my planning worksheet to create a production schedule the start and end times are drastically off. It says I can produce large production orders within minutes, which isn't true.
Am I missing anything? Your help is greatly appreciated.
Thanks again.
Jeff