Hi,
I have written some code to fetch date of project enddate. I have used projtable.ProjectedEndDate to get the date. But functionality I was trying to implement was not working when I debug it then I found instead of date which I gave it is fetching Date 01/01/1900 00:00:00. I think some calendar setup is missing for same. In other environment same code is fetching proper date. Please suggest.
Regards,
Smit Patel
*This post is locked for comments
I have the same question (0)Hi,
Resolved issue. The customized field was getting validated before saving project end date itself. That was the reason it was taking default date. End Date has to be saved before used in any validation.
Thank you!
Regards,
Smit