Production Capacity Planning from Planned Production Order

(0) ShareShare
ReportReport
Posted on by 143

Hi Experts,

Need your help in understanding the Production Capacity Planning from Planned Production Order.

Scenario: Even when the resource is set to Finite capacity still it is getting overbooked once the master scheduling run is completed.

Resource = Finite capacity = Yes, 8 hr a day

Production parameter = Job scheduling, Finite capacity

Master Plan= Finite capacity=yes, Finite capacity time fence is 100 days, Coverage group= Capacity scheduling time fence = 100 days

Run Master plan for BOM item

Planned production order is generated

Approve and Firm PPO

No capacity error. Actual production is getting generated and resource is getting overbooked every time.

pastedimage1629466708036v1.png

pastedimage1629466745151v2.png pastedimage1629466776218v3.png

Even tries turning on and off below parameter in the production control parameter but no impact.

pastedimage1629466823966v4.png

Please help me in understanding the Capacity scheduling concepts in D365 FO. Thanks

I have the same question (0)
  • Aparisi82 Profile Picture
    2,180 on at
    RE: Production Capacity Planning from Planned Production Order

    Can you try to schedule manually the planned orders booking 24 hours in total in your example with finite capacity flag ticked?

    If that works it means it is an Plan configuration issue , if it does not work it means it is a product /route issue

  • Ashish AX Functional Profile Picture
    143 on at
    RE: Production Capacity Planning from Planned Production Order

    Route is having a Resource with Finite Capacity.

  • Aparisi82 Profile Picture
    2,180 on at
    RE: Production Capacity Planning from Planned Production Order

    Hello, you haven't shared the most important piece of configuration which is the production route.

    Have you set the production route requirement on the resource group or specific resource?

    Is the finite capacity flagged on the resourced group?

  • Suggested answer
    Adrian Serban Profile Picture
    on at
    RE: Production Capacity Planning from Planned Production Order

    Hi Ashish,

    I tried to replicate the scenario with the details that you provided; however, I get the expected results.

    If you can constantly replicate this issue, you could create a case with Microsoft support including all the details, so that we can investigate this.

    pastedimage1629972901570v1.png

    Thank you,

    Adrian Serban

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Abhilash Warrier – Community Spotlight

We are honored to recognize Abhilash Warrier as our Community Spotlight honoree for…

Leaderboard > Supply chain | Supply Chain Management, Commerce

#1
CA Neeraj Kumar Profile Picture

CA Neeraj Kumar 1,011

#2
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 279 Super User 2025 Season 2

#3
BillurSamdancioglu Profile Picture

BillurSamdancioglu 215 Most Valuable Professional

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans