Hi Experts,
Need your help in understanding the Production Capacity Planning from Planned Production Order.
Scenario: Even when the resource is set to Finite capacity still it is getting overbooked once the master scheduling run is completed.
Resource = Finite capacity = Yes, 8 hr a day
Production parameter = Job scheduling, Finite capacity
Master Plan= Finite capacity=yes, Finite capacity time fence is 100 days, Coverage group= Capacity scheduling time fence = 100 days
Run Master plan for BOM item
Planned production order is generated
Approve and Firm PPO
No capacity error. Actual production is getting generated and resource is getting overbooked every time.


Even tries turning on and off below parameter in the production control parameter but no impact.

Please help me in understanding the Capacity scheduling concepts in D365 FO. Thanks