Multiple Active Budget Cycles?

(0) ShareShare
ReportReport
Posted on by 215

Dear all,

First of all let me just warn you that I am very new to the budget module and I'm still trying to understanding the basics of it.

Nevertheless, I want to ask you if it is possible to have two different Budget Cycles active at the same time - one from Jan-Dec and other from Oct-Sept. 

Each Budget Cycle (season) is divided into two (sub-seasons). 

The assignment of the respective budget is done by the combination of: 

- Dimension1+Dimension2+Season+Subseason

My question is, in a certain period of time is it possible to have two active budget types and, if so, how can the user assign to one budget instead of the other?

Thanks in advance. 

I have the same question (0)
  • Suggested answer
    Ludwig Reinhard Profile Picture
    Microsoft Employee on at

    Hi Pedro,

    The budget cycles come into play when you make use of the budget control configuration.

    In the assign budget models you can have different budget cycle time spans defined for the same period.

    Yet, the question is why you want to do that?

    What is the business case that you think about?

    Would be great if you could elaborate.

    Many thanks,

    Ludwig

  • Afonso Rodrigues Profile Picture
    215 on at

    Hello Ludwig

    Many thanks for your answer.

    First of all let me just confirm: I can only have one active budget cycle, right?

  • Anrini Profile Picture
    on at

    Hi,

    I hope this blog will help with more info - docs.microsoft.com/.../budget-control-overview-configuration

  • Suggested answer
    Ludwig Reinhard Profile Picture
    Microsoft Employee on at

    Hi Pedro,

    No, you can have multiple cycle control spans active at the same time.

    The question is why you would like to have that?

    I think budgeting and control would be horrible and difficult to maintain.

    Best regards,

    Ludwig

  • Afonso Rodrigues Profile Picture
    215 on at

    Imagine that I have to types of products, and that they have different "season spans".

    So, for the Products Type A, the budget cycle would be Jan-Jun/Jul-Dec.

    For the Products Type B, the budget cycle would be Oct-Mar/Apr-Sep.

  • Verified answer
    Ludwig Reinhard Profile Picture
    Microsoft Employee on at

    Hi Pedro,

    Got your point.

    The way you would cover this seasonality is usually like this:

    Step 1 Create demand/supply/inventory forecast 

    fcst1.png

    Step 2: Enter details 

    Here you can add the seasonality by making use of an allocation key

    fcst2.png

    Step 3: 

    Once your items are "forecasted" you can transfer all of that stuff into the budgeting module by hitting those buttons

    fcst3.png

    Doing things this way makes things much easier. 

    Best regards, 

    Ludwig

  • Afonso Rodrigues Profile Picture
    215 on at

    Hello Ludwig

    Thanks a lot for your help.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

#1
Martin Dráb Profile Picture

Martin Dráb 451 Most Valuable Professional

#2
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 428 Super User 2025 Season 2

#3
BillurSamdancioglu Profile Picture

BillurSamdancioglu 239 Most Valuable Professional

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans