Hi,
What is Capacity in Show Working Hours in Resource Project Service?
Hi,
What is Capacity in Show Working Hours in Resource Project Service?
Hey Rocky,
Capacity for a service or resource defines a limit to the number of activities a resource can perform in a stipulated time. You must set both the capacity of the service and the resources required for the service.
When you set capacity of a resource and service, the service calendar doesn’t allow booking the resources once they reach their capacity.
Set the capacity for a service or resource ::
https://docs.microsoft.com/en-us/dynamics365/customer-service/set-capacity-required-service-resource
Please mark my comments as answered if this helps.
Thanks,
Saurabh
Hi,
capacity is the number of activities a resource can perform in a stipulated time.
https://docs.microsoft.com/en-us/dynamics365/project-service/faq-allocation-methods
Hope it helps,
Marco
If you've found the answer helpful, please mark it as Verified (by clicking 'Yes' under a suggested answer)
Daivat Vartak (v-9d...
225
Super User 2025 Season 1
Muhammad Shahzad Sh...
95
Vahid Ghafarpour
82