I am using project accounting in AX 2012 R3, while creating PO I used the wrong project id and hence the cost has been charged to that project. I want to transfer that cost from wrong project to right project, so is there any suggestion how can it be done. I am aware of the option of passing general journal voucher to reallocate the cost but I am looking for other alternative. Also note that the category of my projects is internal.
*This post is locked for comments
I have the same question (0)Hi Ankag,
You can try to use the adjust functionality to change the project ID.