I am having some trouble with our production picking waves. The Production parameter "Allow Partial Reservation" is set, but when I process our picking waves, no work is created if any of the lines show an Item Allocation Failure. Once the materials are on hand, the wave will process without a problem. First, am I understanding the parameter correctly? We have a production bom that includes 10 lines that need picking. 8 lines can allocation their items, but two lines have zero quantity on hand. (typically, these lines are on a production order that has not yet been completed). Should a wave with "Allow Partial Reservation" enabled be able to create the work for the 8 lines? If so, what settings enable that situation?
Thanks,
LJ
*This post is locked for comments