Hi,
I have a Problem with resource requirements. When creating a work order a resource requirement is generated automatically. The RSO then uses this resource requirement to plan according to it's scheduling method.
The problem is that my resource requirements do not inherit (2) the scheduling method defined for the entity msdyn_workorder (1).
I am glad for anyone who can shed some light on this mistery.
Regards
Jeki
Hi Jeki, I had this issue a while ago and had filed a ticket, but when I tried to re-produce the issue today, everything worked as expected. What URS and RSO version are you on? Feel free to drop me a message at alheinz(at)microsoft.com and I'll try to help.
Open a Ticket with MS support.
Thank you for the responses.
Apparently there was another problem. The duration was not calculated correctly, which resulted in a duration of 0. I did not realize this because on the test system this worked fine.
If the duration is set the RSO plans correctly.
Under review
Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.
Congratulations to our community stars!
Expanding mentorship, skilling, and AI innovation
These are the community rock stars!
Stay up to date on forum activity by subscribing.
11manish 50 Super User 2026 Season 2
Travis South 45
Ayesha Wajahat 18