Hi
i met a requirement like this, suppose i have physically received 1000 items(product receipt posted), the vendor send me two invoices, one with 200, and another with 800. and it happened quite often here. now i have to correct/cancel the purchase receipt and create new one.
The point is sometimes the received items have already been consumed by the production, so it's impossible for me to cancel the receipt.
Is there any best practice to figure out this issue ?
many thanks.