Suggested answer

Preferred Resource in FS Restricting Resources on Schedule Board

(0) ShareShare
ReportReport
Posted on by 40

I have set up a Work Order with a Resource Requirement record that has an associated "Requirement Resource Preferred" record identifying that a specific Bookable Resource that is a User is to be preferred. Based on the documentation from Microsoft (https://docs.microsoft.com/en-us/dynamics365/field-service/resource-preferences), when you search for availability on the schedule board, this resource should show at the top with a heart next to it, then any other resources that fit the requirements with availability should also show in the list. At this time, if I use this preference, I ONLY get that preferred resource, but if I remove the preference, I get a list of about 10 resources that are available. 

Is there a setting that I'm missing? Note that I am not using RSO, this is just a Work Order within Field Service with a Resource Requirement against it, and the Requirement Resource Preferred.

I have the same question (0)
  • Al Iggs Profile Picture
    on at
    RE: Preferred Resource in FS Restricting Resources on Schedule Board

    Hi Tara, just to be sure, I have upgraded my instance to v8.8.11.19 and it still works.

    Before:

    pastedimage1583996869627v3.png

    Added the preference:

    pastedimage1583996829263v2.png

    After:

    pastedimage1583996790605v1.png

  • Tara C Sinclair Profile Picture
    40 on at
    RE: Preferred Resource in FS Restricting Resources on Schedule Board

    Currently I am on version 8.8.11.19 according to my solution management page.

    I created a Work Order, which auto-creates the resource requirement - when I go to "find availability", it shows me 3 resources available.

    I then update the Resource Requirement with a Resource Preference for one of those individuals that appeared on the board and return to the Schedule Board (I have a Default board with all default settings). I select that same Work Order  and Find Availability now that the preference record exists and I only see that Preferred Resource, not the other two.

    I'm not sure whether there is a setting somewhere that I may be missing or what.

  • Suggested answer
    Al Iggs Profile Picture
    on at
    RE: Preferred Resource in FS Restricting Resources on Schedule Board

    I just tried it in my system. Schedule Assistant list 2 matching resources, A and B. When I specify B as preferred and run Schedule Assistant again, I still get the 2 matches and B shows up before A. Exactly as expected and documented. Are you on the latest release (FS v.8.8.x)? There were some changes in this area not long ago. Try it with a brand new board to make sure that there are no configurations that change the standard behavior..

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Mansi Soni – Community Spotlight

We are honored to recognize Mansi Soni as our August 2025 Community…

Congratulations to the July Top 10 Community Leaders!

These are the community rock stars!

Leaderboard > Service | Customer Service, Contact Center, Field Service, Guides

#1
Abhilash Warrier Profile Picture

Abhilash Warrier 100 Super User 2025 Season 2

#2
Suresh Kulla Profile Picture

Suresh Kulla 72 Super User 2025 Season 2

#3
DAnny3211 Profile Picture

DAnny3211 54