web
You’re offline. This is a read only version of the page.
close
Skip to main content

Notifications

Announcements

No record found.

Community site session details

Community site session details

Session Id :
Service | Customer Service, Contact Center, Fie...
Suggested Answer

Preferred Resource in FS Restricting Resources on Schedule Board

(0) ShareShare
ReportReport
Posted on by 40

I have set up a Work Order with a Resource Requirement record that has an associated "Requirement Resource Preferred" record identifying that a specific Bookable Resource that is a User is to be preferred. Based on the documentation from Microsoft (https://docs.microsoft.com/en-us/dynamics365/field-service/resource-preferences), when you search for availability on the schedule board, this resource should show at the top with a heart next to it, then any other resources that fit the requirements with availability should also show in the list. At this time, if I use this preference, I ONLY get that preferred resource, but if I remove the preference, I get a list of about 10 resources that are available. 

Is there a setting that I'm missing? Note that I am not using RSO, this is just a Work Order within Field Service with a Resource Requirement against it, and the Requirement Resource Preferred.

I have the same question (0)
  • Suggested answer
    Al Iggs Profile Picture
    on at

    I just tried it in my system. Schedule Assistant list 2 matching resources, A and B. When I specify B as preferred and run Schedule Assistant again, I still get the 2 matches and B shows up before A. Exactly as expected and documented. Are you on the latest release (FS v.8.8.x)? There were some changes in this area not long ago. Try it with a brand new board to make sure that there are no configurations that change the standard behavior..

  • Tara C Sinclair Profile Picture
    40 on at

    Currently I am on version 8.8.11.19 according to my solution management page.

    I created a Work Order, which auto-creates the resource requirement - when I go to "find availability", it shows me 3 resources available.

    I then update the Resource Requirement with a Resource Preference for one of those individuals that appeared on the board and return to the Schedule Board (I have a Default board with all default settings). I select that same Work Order  and Find Availability now that the preference record exists and I only see that Preferred Resource, not the other two.

    I'm not sure whether there is a setting somewhere that I may be missing or what.

  • Al Iggs Profile Picture
    on at

    Hi Tara, just to be sure, I have upgraded my instance to v8.8.11.19 and it still works.

    Before:

    pastedimage1583996869627v3.png

    Added the preference:

    pastedimage1583996829263v2.png

    After:

    pastedimage1583996790605v1.png

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > Service | Customer Service, Contact Center, Field Service, Guides

#1
Tom_Gioielli Profile Picture

Tom_Gioielli 57 Super User 2025 Season 2

#2
Daniyal Khaleel Profile Picture

Daniyal Khaleel 34 Most Valuable Professional

#3
Scott Jackson UK Profile Picture

Scott Jackson UK 22

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans