Hi all,
We use budget control for purchase orders and work flow for purchase orders in AX 2012 R3 (R2).
In case that there is not enough budget, the system provide warning message and allow to user submit PO to WF.
Is it possible to disable PO submission if there is not enough budget??
The official sources does not provide the clear answer if you can prevent submitting WF if there is not enough budget.
They say "Budget checking is performed on all lines when the purchase order is confirmed and when the purchase order is submitted to a workflow, and then again when the purchase order is approved in a workflow."
If you use PO budget control and there is no over budget user groups, you can't confirm the PO if there is not enough budget.
Thanks for help
*This post is locked for comments
I have the same question (0)