Hello All,
I need help with WBS.
In a work breakdown structure, if you have let's say 5 tasks of 1 hour each, all hapening one after the other (predecessor) and therefore all on the same day, I get some discrepenties error. It says that the task is starting before its predecessor. If I click the Fix schedulling discrepenties error, I end up with one day per task and a 5 days WBS instead of 5hrs.
Any idea how I can fix this? (It works fine in MS Project which tells me the total time is 0.63 days)
Thanks