Hi All,
I have set up Project operations for a client. I have set up Products, PriceLists, and all other stuff related to this.
I have created resources, assigned roles to them, created tasks in the project, and assigned tasks to the resources. Each resource has its price setup Hourly basis. Estimated amounts are also set up correctly.
Now after adding Time Entries for some tasks and approving those tasks by the manager do not shows any amount value in the fields "Actual Labor Cost" and "Estimated Labor Cost" field.
Please have a look at this attachment and guide where I can check to get this amount calculated in the system.
Thanks,