What is the best way to handle project contract change orders?
Ex: If additional work/tasks are added after the project has started outside of the original contract terms. Is there any function that represents a change order?
Hi Nilestone,
The simplest, out-of-the-box way would be this one: Hack #11: How to use the Project Contract inside Dynamics 365 Project Operations? – Part One | Welcome to D365Hacks
Essentially you create a second Contract Line and tie it with the same project, but against new Tasks! Let me know if the blog post helps answer your question, if not I can give you an example.
You can also customize the tool with this route, Antti Pajunen has blogged about it in the past: Change Requests in Project Operations – Part I – Antti Pajunen – Learning, sharing, community
Please, mark this as answered so other can benefit from it.
Thanks,
www.d365hacks.com
Under review
Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.
Congratulations to our 2026 Super Stars!
We are thrilled to have these Champions in our Community!
These are the community rock stars!
Stay up to date on forum activity by subscribing.
Giorgio Bonacorsi 616
André Arnaud de Cal... 460 Super User 2026 Season 1
Syed Haris Shah 331 Super User 2026 Season 1