What is the best way to handle project contract change orders?
Ex: If additional work/tasks are added after the project has started outside of the original contract terms. Is there any function that represents a change order?
Hi Nilestone,
The simplest, out-of-the-box way would be this one: Hack #11: How to use the Project Contract inside Dynamics 365 Project Operations? – Part One | Welcome to D365Hacks
Essentially you create a second Contract Line and tie it with the same project, but against new Tasks! Let me know if the blog post helps answer your question, if not I can give you an example.
You can also customize the tool with this route, Antti Pajunen has blogged about it in the past: Change Requests in Project Operations – Part I – Antti Pajunen – Learning, sharing, community
Please, mark this as answered so other can benefit from it.
Thanks,
www.d365hacks.com
Under review
Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.
As AI tools become more common, we’re introducing a Responsible AI Use…
We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…
These are the community rock stars!
Stay up to date on forum activity by subscribing.
Martin Dráb 660 Most Valuable Professional
André Arnaud de Cal... 549 Super User 2025 Season 2
Sohaib Cheema 307 User Group Leader