Ax Job Scheduling.

(0) ShareShare
ReportReport
Posted on by 344

Hi all

Is it possible to split a planned job? I want to split a planned job to be planned in smaller parts: If I have big job (a production to stock) and I want the operators to work with this between other jobs.

Br EG

*This post is locked for comments

I have the same question (0)
  • Suggested answer
    Weaveriski Profile Picture
    23,620 Moderator on at

    Yes, in the planned screen in the maintain section of the action pane there is a split option.

  • EGrotberg Profile Picture
    344 on at

    Hi Steven. Thank you for you answer. This is very helpful and it can be a solution for me. What if you have a production job? Can you split production jobs?

  • Weaveriski Profile Picture
    23,620 Moderator on at

    Well you can on the creation of the job in theory, it depends when you know and how the split is occurring, I am guessing you are wanting to do this to push it to another machine or something which means the scheduling and capacity will be wrong because it is scheduled.

  • EGrotberg Profile Picture
    344 on at

    Thanks again for your answer. I am running jobscheduling daily . I have very short delivery terms for my orders (3 days) except order to increase stock. Normally my jobs are very small, but order for stock can be big. I am planning forward and when I run jobscheduling I realize that I should split my jobs beacuse I do not have a enough capacity to produce the total quantity.

  • Weaveriski Profile Picture
    23,620 Moderator on at

    That might also constitue looking at the order sizes of those items to get AX to split them into more manageable sizes for pushing the stock elements into the plan and not impacting on capacity so much.

  • EGrotberg Profile Picture
    344 on at

    Yes I am agree. The split option in the planned screen you mentioned is also a good solution to split orders into more manageable sizes. Thanks again

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > 🔒一 Microsoft Dynamics AX (Archived)

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans