Production order - rework. Scheduling options disabled at estimate.

(0) ShareShare
ReportReport
Posted on by

Hi,

Does anyone know why a rework batch order does not allow operations or job scheduling at the "estimated" status.

These options are normally available when a production/batch order is estimated but when the order is flagged as rework they are disabled until order is "released".  If flag changed on order (via table) the options enable. 

I'm sure we can work around this but would like to know the logic behind it.  Only thing I can think of is that a rework is expected to be unplanned rather than planned so scheduling is not seen as applicable until the job is flagged as with the production floor but it would be best to make sure capacity exists on the resource for the rework before releasing in many instances even when process is rework.

Regards, Paul

AX 2012 R3 CU8.

*This post is locked for comments

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

News and Announcements

Now Available: 2025 Release Wave 2

Quick Links

Ramesh Kumar – Community Spotlight

We are honored to recognize Ramesh Kumar as our July 2025 Community…

Congratulations to the June Top 10 Community Leaders!

These are the community rock stars!

Announcing the Engage with the Community forum!

This forum is your space to connect, share, and grow!

Leaderboard > 🔒一 Microsoft Dynamics AX (Archived)

#1
Kempeth Profile Picture

Kempeth 4

#1
Andy Adamak Profile Picture

Andy Adamak 4

#1
Community Member Profile Picture

Community Member 4

Featured topics

Product updates

Dynamics 365 release plans