Hello,
I have single workcentergroup (A) with attached 3 workcenters (B,C,D) in this group. I have defined 3 qty of workcenter in route to allocate the multiple workcenters when we run the master plan. Now when I check the results in plan orders it shows like this
| Operation | Priority | Workcenter | Start time | End time |
| 10 | Primary | B | 10:00 | 20:00 |
| 10 | Primary | B | 10:00 | 20:00 |
| 10 | Primary | B | 10:00 | 20:00 |
Logically instated B Workcenter on the 2nd and 3rd line, it should have to show C and D Workcenter.
I am using Finite capacity.
Can anyone please tell that what setup I am missing to get Workcenter C and D in 2nd and 3rd line.
*This post is locked for comments
I have the same question (0)Do you have finite capacity on your work centers and group as well as running scheduling with finite capacity?