Production order "Error qty"

(0) ShareShare
ReportReport
Posted on by 420

Hi,

I am using standard costing. I create a Production order with 10 Qty.

I run the production order and produce 3 part and when I enter the RAF journal, the Good qty is 2 and Error qty =1 (scrap) . After i post, why Ax still show that i have "remaning reported as finish" = 8? I expect it to show 7. Can someone explain how Error qty work in Ax2012?

Beside that, Ax had consume 3 qty of BOM line item.

The Error qty post to which ledger journal?

Kindly advice. thanks.

*This post is locked for comments

I have the same question (0)
  • Suggested answer
    André Arnaud de Calavon Profile Picture
    301,171 Super User 2025 Season 2 on at

    Hi Kongyu,

    Error qty means that you tried to produce items, but they failed a quality check or something. So the BOM items are consumed, you may have spent time and machines to produce, but maybe due to a cutting failure, it is not a good product.

    The production order is set to produce 10 (good) items. So this is the reason why you have 8 remaining. In total you might have used BOM materials for 11 products, but the good quantity is only 10. Depending on the cost model, the consumed materials and route operations will determine a higher cost per unit.

  • Community Member Profile Picture
    on at

    Are transactions of error quantities posted anywhere for tracking and accounting?

  • Fredrik Sætre Profile Picture
    12,644 on at

    If you set it up. It could be allocated as general production cost for the finished goods or as a separate accounting.

  • Suggested answer
    guk1964 Profile Picture
    10,888 on at

    Basically the system believes what you tell it- you told it you wanted to make 10 pieces- not that you wanted to make 1 as scrap so you need to make another 8, and it will base its variance analysis on that quantity.  In this case you will need to issue more material to  make the extra piece, to compensate for the scrap item.

    If you want to change that logic, then receive the faulty item as good and then scrap it  from inventory.

  • Community Member Profile Picture
    on at

    Hi Fredrik,

    Is there any information on how to setup up the cost structure to account for the error qty in a separate account? Any information is greatly appreciated.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > 🔒一 Microsoft Dynamics AX (Archived)

#1
Martin Dráb Profile Picture

Martin Dráb 4 Most Valuable Professional

#1
Priya_K Profile Picture

Priya_K 4

#3
MyDynamicsNAV Profile Picture

MyDynamicsNAV 2

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans