Hello Friends,
For one of the operations, it takes the 24 hours as a fixed run time, irrespective of the quantities to be manufactured.
How can we setup the route to achieve the same?
I tried to set route consumption calculation as 'Capacity' with Capacity = 1 and Factor = 24 but with this setup system did not allow me schedule the order saying there is no enough capacity.
Is this a bug or I am missing some setup?
I took a reference this article:
http://www.dynamicsaxtraining.com/production_training/routes-and-operations
Regards
-Rahul
*This post is locked for comments
I have the same question (0)