Hi All,
We have been using jobs in BC and we know how to change the status of for the whole job however is there a way to change status at task or planning line level
Thanks
do we have status field on task level? May be I am missing this..
status on Job Planning lines will come from Job status field and is a non-editable field.
why do you want to change at those levels?
Job tasks will be closed in a different sequence to the whole job much like when you create a plan in MS project. We want to close tasks completed so for example we can run report with open tasks etc. I guess the requirement is pretty normal in "project" type of module
but it is not available in Standard BC.
Under review
Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.
As AI tools become more common, we’re introducing a Responsible AI Use…
We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…
These are the community rock stars!
Stay up to date on forum activity by subscribing.
OussamaSabbouh 2,990
Jainam M. Kothari 1,576 Super User 2025 Season 2
YUN ZHU 1,028 Super User 2025 Season 2